John Rogers
John Rogers Elementary School Replacement Project
John Rogers Elementary School has moved to the interim site at John Marshall School, 520 NE Ravenna Boulevard, for the 2023-24 and 2024-25 school years.
Timeline
![construction phase graphic showing that the school is in the Construction phase](http://www.seattleschools.org/wp-content/uploads/2022/08/ConstructionProgress_6_Construction-1024x124.png)
- Pre-design phase complete
- Schematic design phase complete
- Design development phase complete
- Construction documents and permitting phase complete
- Bid and award phase complete
- Construction is in progress
- School opens Fall 2025
About the Project
The existing school building will be demolished, and a new school building will be constructed. Site work will terrace the site and seamlessly connect the play field to the rest of the campus.
Designed for current and future students
The proposed design replaces the existing John Rogers Elementary School with a new, 82,000 square foot 2- and 3-story building. Once complete, the school will provide an equitable learning space for up to 500 K-5 elementary students and an area to expand the school in the future as enrollment grows.
Thanks to the work of the School Design Advisory Team (SDAT) — comprised of school leaders, parents, and community members — it will meet district educational standards for 500 students while also fulfilling the specific needs the specific needs of the John Rogers Elementary School community.
The school will nestle into a newly terraced site that will enhance connections to nature, play, and outdoor learning. Campus improvements will provide a safe site for all. A new network of pathways and street access will connect the neighborhood to the school.
Outdoor learning areas will be improved, including a new natural turf field and drainage system. Natural play areas will connect students to the site.
Safety and security
Visitors will enter through a secure main entrance that invites you into the administrative office for check-in before entering the school. All other doors will be locked during the school day.
Building for a sustainable future
The new John Rogers Elementary is being designed as Seattle Public Schools’ first Net-Zero Energy building, and includes:
- Daylight in all classrooms and learning spaces
- Highly efficient heating and fresh air ventilation
- Geothermal wells to use energy from the ground for heating and cooling
- Solar panels to use energy from the sun
Project Progress
Live Video Feed
Construction Update
Project updates are posted for the previous month the week after the monthly BEX and BTA Capital Levies Oversight Committee meetings.
![aerial view of a construction project with a large H-shaped building in progress. Behind it is a open dirt area with construction equipment. Trees are all around and a lake is visible in the far background.](http://www.seattleschools.org/wp-content/uploads/2024/07/JRES-JUNE-2024-01-300x214.jpg)
![a large building under construction with a 3 story section covered in yellow material with writing and a section that has a sloped roof](http://www.seattleschools.org/wp-content/uploads/2024/07/JRES-JUNE-2024-02-300x214.jpg)
![looking out through a wall framing without walls toward another building that has yellow sheathing on it](http://www.seattleschools.org/wp-content/uploads/2024/07/JRES-JUNE-2024-05-300x214.jpg)
![inside a partially constructed hallway with metal studs and people working](http://www.seattleschools.org/wp-content/uploads/2024/07/JRES-JUNE-2024-06-300x214.jpg)
![inside a partially built room with wood beams and steel framing](http://www.seattleschools.org/wp-content/uploads/2024/07/JRES-JUNE-2024-07-300x214.jpg)
![wood framing on a concrete floor inside a partially constructed building](http://www.seattleschools.org/wp-content/uploads/2024/07/JRES-JUNE-2024-08-300x214.jpg)
June 2024
- Work on the lower field continues with under-field drainage begining.
- Continued exterior metal studs and sheathing with approximately 50% finished by the end of June.
- Continued interior metal stud framing and rough-in for utilities.
- Began roof work.
July 2024
- Continue interior and exterior framing, exterior sheathing, and roofing work.
- Continue work on drainage under the lower field.
Progress Photos
Current Designs
Site plan
![architect's rendering of a site plan with a building in the center, a large green field to the right, and a circular driveway to the left](http://www.seattleschools.org/wp-content/uploads/2023/09/JRES-AUG-2023-02-1024x419.jpg)
Here is the presentation from the meeting.
Questions and Answers from Community Meetings
Below you will find the questions/comments and answers from community meetings
School Design Advisory Team (SDAT)
Early in the design process, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, parents, and community members. Students are sometimes included for all or part of the process. The project construction managers also take part. Learn more about the John Rogers Elementary School SDAT.
More information
Site size: The 9.1 acre site is partially in the flood plain for Thornton Creek.
Architect: DLR Group
General Contractor/Construction Management Firm (GC/CM): Lydig Construction
Project Budget: $91.5M
Funding Source: Funded by the Building Excellence V (BEX V) Capital Levy, approved by Seattle voters in 2019.
Contact
For questions or comments about this project, please use our online Let’s Talk form.
Project Manager: Amanda Fulford, asfulford1@seattleschools.org, 206-252-0697
John Rogers Elementary School
4030 NE 109th St
Seattle, WA 98125