Projects

Coe

Coe Elementary School Classroom Addition

graphic showing project phases; see timeline below

Find out what happens during each phase

Timeline

  • Pre-design phase complete
  • Schematic design phase complete
  • Design development phase complete
  • Construction documents/permitting phase complete
  • Bid and award phase complete
  • Construction in progress
  • Addition opens after Thanksgiving Break 2021

Recent Progress

Progress updates are posted for the previous month the week after the monthly BEX and BTA Capital Levies Oversight Committee meetings. These meetings typically take place on the first Friday of each month.

Major Activity in September 2021

  • Continued roofing; work nearly complete
  • Began siding installation
  • Continued window installation; work nearly complete
  • Completed interior stairs
  • Began interior painting
  • Continued mechanical, electrical, and plumbing installation

Major Activity Planned for October 2021

  • Install flooring and casework
  • Install doors and hardware
  • Install wall coverings
  • Continue mechanical, electrical, and plumbing trim out
  • Install audio-visual equipment
  • Continue bio-retention pods, irrigation, and landscaping

Project Photos

Click on an image to view photos and captions

About the Project

The original Frantz Coe Elementary School, built in 1907, was destroyed by fire in 2001. The current 75,214-square-foot building was constructed in 2003. This project will construct a six-classroom addition.

Design : Mahlum Architects

Construction: Western Ventures Construction, Inc.

Funding Source: Funded by State of Washington Distressed Schools Grant.

Contacts

Let’s Talk Comments and Questions form

Project Manager : David L. Jackson, 206.735.8957, dljackson2@seattleschools.org

Frantz H. Coe Elementary School

2424 7th Ave W
Seattle, WA 98119

School Profile

School Website