    Construction Update: February 2020
    Posted on 02/24/2020
    Structural steel for new classroom addition

    Three Projects Under Construction

    Work continues on the levy-funded construction projects at Daniel Bagley Elementary, Wing Luke Elementary, and Webster School.

    Daniel Bagley Elementary 

    At Bagley, the structural steel for the new classroom addition is in place (shown above) and the concrete has been poured for the first and second floors. 

    a concrete floor in a building under construction

    Work on the roof of the new gym is underway.

    In the existing landmarked building, framing and wallboard installation continues on the first floor, and painting and ceiling grid installation is underway on the second floor. Because the ceiling is uneven in some areas, furring strips were installed before ceiling work could begin. The project will be ready for students to begin school on Sept. 2, 2020. (Learn more about this construction project.)

    Wing Luke Elementary 

    Wing Luke’s three new buildings can be clearly seen from the aerial view.

    an aerial view of a construction site

    Wall framing is complete in Building A, which will house the main entry, administration offices, and classrooms. Workers began installing door frames and wallboard. Building B, with the library and classrooms, now has the second-floor concrete deck in place, and the glue laminated timber (glulam) structural beams were installed in the library.

    photo of a building under construction with large beams and construction equipment

    Steel is being erected and roof trusses installed over the commons and gymnasium in Building C. The new Wing Luke Elementary will open in Fall 2021. (Learn more about this construction project.)

    Licton Springs at Webster School

    The roof is complete on the historic Webster School building, and the new windows have been installed. Earthquake safety (seismic) reinforcement work continues. Interior metal-stud framing continued with the first floor complete and the second floor in progress. Masonry veneer has been installed on the gymnasium addition, and slab-on-grade concrete was poured.  Structural steel erection is complete for the portion of the addition that connects the new gym with the historic school building. Roof installation is in progress.

    photo of a concrete floor in a building under construction

    photo of a large building with roofing underway

    Webster will open this fall as the new home of Licton Springs K-8. (Learn more about this construction project.)

    Other Project Updates

    Planning continues for the additions at Coe Elementary, Magnolia Elementary, West Seattle Elementary, and West Woodland Elementary, as well as for replacement of Rainier Beach High School, Kimball Elementary, Northgate Elementary, and Viewlands Elementary. You can see all of the current projects on the construction page. Project updates are posted monthly.