    Leschi Elementary School Classroom Addition

    project phase graphic

    Learn what takes place during these design and construction phases

    Timeline

    • Predesign phase complete.
    • Schematic design phase complete.
    • Design development phase in progress.
    • Construction documents and permitting phase begins Fall 2020.
    • Bid and award phase begins Spring 2021.
    • Construction begins Summer 2021.
    • Estimated completion: Spring 2022.

    About the Project

    A two-story addition will be constructed to hold four classrooms to address student enrollment growth. The main entrance and administration area will be modernized to create a secure entry vestibule that directs visitors into the office area. 

    Leschi Elementary School will remain occupied during construction. 

    Project Manager: Brian Fabella, brfabella@seattleschools.org, 206-252-0702

    Project Design: TCF Architecture

    Construction: TBD

    Funding Source: Washington State Distressed Schools Grant

    Project Updates

    July/August 2020

    • Received 100% design development drawings
    • Beginning the SEPA process