    Timeline

    • Predesign phase complete.
    • Schematic design phase in progress.
    • Design development phase begins Summer 2020.
    • Construction documents and permitting phase begins Fall 2020.
    • Bid and award contracts phase begins Winter 2021.
    • Construction phase begins Spring 2021.
    • Addition opens Fall 2022.

    Project Overview

    A 12,500-square-foot classroom addition will be constructed at Madison Middle School to accommodate enrollment growth.

    Project Manager: Vince Gonzales, vrgonzales@seattleschools.org, 206-252-0151

    School Design: Studio Meng Strazzara

    Funding Source

    Funded by State of Washington Distressed Schools Grant