About the Project
This project is the second phase of the Lincoln High School modernization project. The first phase was completed in 2019, allowing the school to open as a new attendance area high school in Fall 2019.
Phase I focused primarily on the historic buildings on the west side of campus. Phase II is focused on the existing buildings on the east side of the campus.
The project includes voluntary seismic improvements to the 1959 east addition, and theater, Career & Technical Education classroom, and gymnasium improvements.
Design: Mahlum Architects
Construction: Lydig Construction
Construction Management: CBRE Heery, Inc.
CBRE Heery Senior Project Manager: Jennifer Everett
Project Budget: $29.0M