Timeline:
- Pre-design phase begins Winter 2021
- Schematic design phase begins Fall 2021
- Design development phase begins Winter 2022
- Construction documents/permitting phase begins Summer 2022
- Bid and award phase begins Winter 2023
- Construction begins Summer 2023
- School opens Fall 2025
About the Project
The Building Excellence V (BEX V) Capital Levy will fund a new replacement school building for Alki Elementary School. It will also provide technology equipment and services, such as computers, peripherals, printers, and other technology for teaching and learning.
Project Budget: $66.9M
Funding Source: Funded by Building Excellence V (BEX V) Capital Levy project, approved by Seattle voters in 2019.