    Wing Luke Elementary Replacement Project

    drawing of the new Wing Luke building

    About the Project

    Opened in 1971, the Wing Luke Elementary building had several major systems and structural challenges. The existing Wing Luke Elementary School will be replaced with a new school building, which was designed in close collaboration with the school community. It will celebrate and facilitate education and programming with a modern school designed to 21st century standards.

    The new 82,000-square-foot school is designed for up to 500 elementary students, grades K-5. It will include six classrooms with toilets for kindergarten or grade 1, 16 classrooms for grades 1-5, four special education classrooms, one resource room, one occupational/physical therapy space, an art room, a music classroom, two early learning spaces, four learning commons, small group learning areas, a gymnasium, a library, a lunchroom/commons, and administration spaces. The core facilities (administrative, commons, gym) are sized to support 650 students, and the campus Master Plan includes a design for a 150-student addition.

    During construction, the Wing Luke Elementary school community is located at an interim site at Original Van Asselt School.

    Design: NAC Architecture

    Construction: Phase I, Rhine Demolition; Phase II, Jody Miller Construction

    Construction Management Firm: CBRE | Heery

    Construction Manager, CBRE | HEERY Van Nguyen

    Timeline

    • Phase I (demolition and site preparation): Complete
    • Phase II construction begins: Summer 2019
    • Expected construction completion: Winter 2021
    • Expected school opening: Fall 2021

    Funding Source

    Funded by the Building Excellence IV (BEX IV) Capital Levy, which was approved by Seattle voters in 2013 and the Buildings, Technology, and Academics/Athletics III (BTA III) Capital Levy, which was approved by Seattle voters in 2009.

    Project Budget

    $47.5 million

     

    Virtual Tour

    Watch a virtual tour of the design for the new facility highlights the significant exterior and interior features that will make it a home for this vibrant learning. NAC Architecture's video is visual tour only without narration or captions.

     

    Project Updates

    Updates are posted for the previous month the week after the monthly BEX and BTA Capital Levies Oversight Committee meetings. These meetings typically take place on the first Friday of each month.

    • Building A: Administration, art, special education, classrooms.
    • Building B: Kindergarten classrooms, classrooms, library connecting buildings B and C.
    • Building C: Gymnasium, commons, kitchen

    December 2020

    Site

    • Continued street improvements on S. Kenyon St., 37th Ave. S, and Rose St.
    • Installing landscaping in north and west areas
    • Continuing hardscape in south area
    • Began playground equipment and bench installation in south area

    Mechanical, Electrical, Plumbing, Fire (MEPF)

    • Continued trim work
    • Continued communications room buildout
    • Began commissioning efforts including boiler startup

    Interior  

    • Striped and sealed gymnasium floor
    • Continuing ceiling tile and resilient flooring installation

    Equipment

    • Installed gym equipment
    • Installed projectors and networking hardware 

     

    Contact Us

    Please send us your questions or comments with the form below.

    Wing Luke Elementary School
    3701 S Kenyon St.
    Seattle, WA 98118

    School Profile

    School Website

    Construction and COVID-19

    Contractors working on district projects are required to comply with the state’s Phase 2 Construction Restart COVID-19 Job Site Requirements. This includes developing a comprehensive COVID-19 exposure control, mitigation, and recovery plan.

    More information on construction and COVID-19 