    Daniel Bagley Elementary Modernization and Addition Project

    drawing of an aerial view showing additions on the back of the school building


    Funding sources: Building Excellence IV (BEX IV) Capital Levy, which was approved by Seattle voters in 2013, and Buildings, Technology, and Academics IV (BTA IV) Capital Levy which was approved by Seattle voters in 2016.

    Timeline

    • Construction start: Summer 2019
    • Estimated school opening: Fall 2020

    About the Project

    Bagley Elementary opened in 1930 and currently accommodates 353 students.

    The Seattle Landmarks Review Board has designated some features of the building as landmarks, including the main stairways, the student dining hall, and the exterior. Care will be taken to preserve or restore these historic features.

    This project renovates the existing building. A two-story classroom addition will add eight new classrooms, and a new gymnasium addition will be more than double the size of the existing gym.

    Once completed, the school will have approximately 58,500 square feet for up to 500 students, and consisting of the 39,000 square-foot historic elementary, 13,000 square-foot classroom addition, and 6,500 square-foot gymnasium addition.

    The school community has relocated to John Marshall School while their building is under construction.

    Design: Miller Hayashi

    Construction: Lydig Construction, Inc.

    Construction Management: Sheils Obletz Johnson (SOJ)

    Project Updates

    September 2019

    • Almost all of the interior demolition and hazardous material removal has been completed.
    • The storm water management system has been installed.
    • Excavation for the new classroom wing and installation of concrete footings continued.
    • Work continued on earthquake safety improvements in portions of the gym and cafeteria.
    • Roof replacement started on the existing building.
    • Masonry and window restoration work has started.