Seattle Public Schools
Home | Academics | Schools | Enrollment | News and Calendars | For Families | For Students | Superintendent | School Board | About Us | Careers at SPS | The SOURCE
 2008-09 Interim Site
 2007-08 Interim Site
 BEX Programs Oversight Committee
 Building Rentals/Leases/Sales
 Capital Levy/Bond
 Capital Projects
 Construction Terms
 Contractor Info/Bid
 Design Standards
 Drinking Water Quality
 Facility Condition Report
 Facilities Map
 Facilities Master Plan
 News & Resources
 Playfield Projects
 Property List
 Self Help Program
 Small Works Roster/HUBs
 Contact Us
 Facilities Home
 Site Map


For problems or questions
regarding this
departmental page,

please contact
Facilities
 
Facilities

 

Cleveland High School
5511 15th Avenue South
Seattle, WA 98108

Interim Site for 2005-07
5950 Delridge Way SW
Seattle, WA 98106
(206) 252-7800

 

Project Description       

 

Project consists of partial demolition of the existing historic 1927 building and complete demolition of the existing gymnasium, renovation of the remaining landmark historic portions that have significant facades, modernizing the 1927 building, adding a new gymnasium/commons building and a new three story classroom building.  Plan is to include plazas and open up 15th Avenue to pedestrian traffic.  Renovation will expand student capacity to 1,000 students from the current 783.  Total facility after renovation is approximately 172,000 gross square feet. 

Building Size 170,000 gross square feet
Capacity 1,000 students (grades 9-12)
Site Size 8.56 acres 
Estimated Cost $67 million
Schedule Start of construction summer 2005;  finish of construction fall 2007
Architect Mahlum Architects
Contractor Absher Construction

               

Cleveland Web Site

Site Map | Business with SPS | Contact Directory | Feedback | Terms
©2007 Seattle Public Schools   All rights reserved
Printer Friendly Version of this Page  
Google
 
 WWW    Seattle Public Schools