Nathan Hale High School
FALL CONSTRUCTION UPDATE
Read as
PDF
Raider Rebuild Underway
Summer was a busy time for the Nathan Hale High School
modernization project. We successfully completed the City's Master
Use Permit process and obtained building permits for the Raider
Parkway classroom portables and the first phase of the new
library/arts addition, called Project 1A, which is now underway. A
new gas service was installed from 30th Avenue NE. We also
performed hazardous materials abatement in the main building
ceiling, abated and demolished the old portables P1 through P3 and
covered walkway, and renovated the former daycare portable into a
3D art classroom. Temporary classroom portables (P1 through P8)
were set up in the south parking lot. Finally, the athletic field
turf was replaced at both Hale and Summit K-12.
Current Events - Projects 1A and 1B
The Project 1A contractor Condon-Johnson has begun installing
50-foot deep auger-cast piles for the new library/arts addition on
the east side of the building. This work is expected to last
through the month of September. Heavy construction should be
minimal during the month of October while we bid and award the next
phase, Project 1B, which is the new 27,000 square foot addition and
renovation project. This includes the new library, art classrooms,
KNHC radio station, and a new fitness center. Construction of
Project 1B is scheduled to start in November and be completed by
fall 2009.
Parking and Traffic
There have been many questions about the temporary impacts on
parking and traffic due to construction at Hale. Placement of
portables in the south parking lot has eliminated approximately 65
parking stalls, and 60 parking stalls are lost from the east lot
due to construction. We have been communicating in a variety of
ways with students, staff, parents, and neighbors about the issues
and how to minimize the impacts. Judging by the great first week of
school, it appears that students and staff are adjusting to the
changes. The Summit K-12 lot can be used for overflow parking,
especially during events such as the first home football game,
soccer match, or Curriculum Night on September 25. We encourage all
Hale students and staff to show respect for your Hale neighbors,
and please stay out of the construction area.
Project 2 - The Big Renovation
Meanwhile, the project team is continuing design of Project 2,
which includes the renovation of the main building including the
offices, academic core, cafeteria and commons, and athletic
facilities. Absher Construction of Puyallup has been selected to
participate during design and to manage the construction of Project
2. We are excited to have a local partner involved so early in the
process to help ensure the project is a success. The design team
will soon schedule meetings with Hale staff to discuss and plan for
Phase 2.
More questions?
Please contact the Nathan Hale project manager, Ian Kell, at
(206) 679-4869 or ikell@heery.com if you have any
questions or concerns.
The Building Excellence program school Hotlines are routinely
updated to provide you with the most current information and
activities about your school of interest ??? dial (206) 368-4082
and press 2 for current information regarding the Hale
renovation.
BEX Telephone Hotline: (206) 368-4082
The Seattle Public Schools' Building Excellence Hotline allows
community members and interested parties to access or request
information about the following BEX Schools:
- Chat with an Operator
- Denny Middle
- Nathan Hale High
- Ingraham High
- Hamilton High
- South Shore K8
- Chief Sealth High
- South Lake
- Garfield High
When you call about one of these schools you may select from the
menu provided. The school hotlines are routinely updated to provide
you with the most current information and activities.